Oakville construction on Lakeshore works towards November completion

Published October 9, 2020 at 6:26 pm

The Town of Oakville has provided an update on the Lakeshore Rd. construction and streetscape project.

Work that is currently happening now includes:

The Town of Oakville has provided an update on the Lakeshore Rd. construction and streetscape project.

Work that is currently happening now includes:

Trafalgar to Dunn

  • Granite pavers north side
  • Placement of granular road base
  • Remove temporary light poles
  • Concrete laybys being poured
  • Placing granular material at Dunn intersection and installation of granite curbs

Dunn to George

  • Roadway closed to traffic while Dunn intersection being excavated
  • George east side concrete sidewalk installation

Trafalgar – Lakeshore to Randall

  • Start underground work associated with fibre optic communication cable relocation and installation of new signals

The $20 million project through the heart of Oakville’s downtown began in April of 2019 and is expected to be completed next month.